Tesla to Riley Line

CZPN: ETLN002
TSP: ETT
Region: Panhandle
Project Type: Transmission Line
CCN Status: Approved
CCN Filing Date: 8/18/2010 (Actual)
CCN Final Order Date: 12/20/2010 (Actual)
Construction Start Date: 5/14/2012 (Actual)
Construction Finish Date: 6/2/2013 (Planned)
In Service Date: 6/28/2013 (Planned)
Project Description: Double-circuit 345-kV CREZ transmission line to be constructed between the Tesla Substation near Childress Texas to the Riley Substation near Vernon Texas.
 


 